Use the Gantt
Read the project over time, change the scale, collapse phases and move or stretch bars with the mouse or the keyboard.
On this page
The Gantt shows the project over time: the WBS on the left and one bar per row on the right, with the dependency arrows, the critical path in red and the baseline as a gray bar under each task. It is the view the project desk opens with.
Before you start
To see the Gantt, you only need to be able to see the desk.
To move bars, create rows or draw dependencies, you must be a Lead or Member of the desk.
What you see at the top
Below the title there are five project indicators:
Indicator | What it shows |
|---|---|
Progress | Progress of the whole project, weighted by effort (or by duration if there is no effort) |
Planned finish | The date the last task finishes according to the current calculation |
Variance | Working days of difference between the planned finish and the baseline finish. It says (no baseline) if you haven't taken a snapshot yet |
On critical path | How many tasks and milestones are on the Critical path |
Overdue milestones | Milestones whose date has passed without being met |
The header buttons are New row, Dependency, Snapshot baseline (Lead only) and Status report.
How to read the chart
Table on the left: columns WBS, Name, Start, Finish and %. The name opens the item record. When you hover over a row, the Edit pencil appears.
Bars: a task is a bar with the completed part darker. A phase is a thin bar with downward tips. A milestone is a diamond.
Red: the bar, diamond or arrow is on the critical path.
Thin gray bar under a task: where it was in the baseline.
Dotted line labeled Today: today's date in the project time zone.
Shaded columns: the Non-working days (for example, Saturday and Sunday) and the Holiday days of the project calendar. Hover over a holiday to see its name.
Below the chart, the legend says which calendar the project uses. If it says "Calendar: Monday to Friday (no holidays: the project calendar could not be read)", your role can't read calendars: the Gantt shades Saturday and Sunday, but doesn't mark holidays. The dates are still calculated with the real calendar.
Change the view
Day, Week or Month: the chart scale. Elion ITSM remembers your choice in this browser.
Today: moves the chart to today.
Collapse phases: hides the tasks and leaves only the phases; the button changes to Expand all. You can also collapse or expand a row with the arrow next to its name.
Baseline: shows or hides the gray baseline bars.
View as list: opens the Build the plan in the list, which is easier on narrow screens.
Move a task with the mouse
Drag the body of the bar to move all of it.
Drag the left edge to change the start, or the right edge to change the finish.
Release. While Elion ITSM saves, the bar looks dimmed.
When you release, the server decides the final date: it respects working days, predecessors and constraints, and moves the tasks that depend on this one. If it doesn't accept the change, the bar goes back to where it was and a message explains why.
Moving a task is the same as saying "start no earlier than" that date (see Date constraints). If a predecessor is later delayed, the task still shifts forward.
Phases can't be dragged: they are calculated from their rows.
Milestones can only be moved; they have no duration.
Move a task with the keyboard
Press Tab until you reach the bar (the row becomes selected).
Use the left and right arrows to move it one day. With Shift, it moves one week.
With Alt and the arrows, you change only the finish.
Press Enter to save. If you didn't move anything, Enter opens the Edit form.
Press Escape to discard; the screen reader announces "Change discarded". Leaving the bar without pressing Enter also discards the move.
The up and down arrows go to the bar on the previous or next row.
Edit a row
Press the Edit pencil in the table or double-click the bar. In a task's form you change the title, the plan dates, the duration, the effort, the progress, the actual dates and the constraint; in a phase's form, only the title. Change the Finish or the Duration (working days), not both at once: one is calculated from the other. If a row is selected when you press New row, the form already suggests where to place it: inside the selected phase or, if you selected a task or a milestone, right after it and on the same level.
What happens next
The indicators, the critical path and the arrows update with what the server calculated.
If other tasks moved, a message says how many successors changed.
Other people who have the project open see the change without reloading.