Status report

Prepare the draft of the weekly project report in one click, with progress, projected finish, late critical tasks and milestones, and copy it as text.

On this page

The Status report builds the draft of the weekly project report with the plan's numbers: actual and expected progress, projected finish date against the baseline, late critical tasks and the variance of each milestone. You copy it as text and paste it into an email or a chat.

Before you start

  • You only need to be able to see the project desk.

  • Your company's plan must include the Elion assistant. If it doesn't, you'll see "Could not prepare the report: your plan or role does not include the Elion assistant".

  • For the report to show variances, the project needs a current Baseline.

  • Record progress before preparing it: the report uses what has been reported (see Record progress).

Steps

  1. Go to the project and choose Gantt or Milestones.

  2. Press Status report.

  3. Review the draft in the Status report window.

  4. Press Copy as text. The button changes to "✓ Copied".

  5. Paste the text where you're going to share it and add your comments.

If the browser doesn't allow copying to the clipboard, Elion ITSM shows the text in a window so you can copy it by hand.

What the report includes

Summary

A paragraph with:

  • Project progress and the progress expected by today, for example "Project progress: 42% (expected by today: 50%).".

  • Projected finish: the finish date according to the current calculation and how many working days it is ahead of or behind the baseline. Without a baseline, it says so. It's the same date as the Gantt's Planned finish indicator.

  • How many critical tasks are late.

  • The next milestone and its date.

  • If there are tasks that don't respect their Date constraints, how many there are.

Late critical tasks

The Critical path tasks whose finish date has passed or whose progress is more than 15 points below what's expected, with their number and name. If there are none, it says "No late critical tasks.".

Milestones

A table with each project milestone in date order:

Column

What it shows

Milestone

Number and name

Date

Current milestone date

Variance

Working days against the current baseline (in red if it slipped)

If the project has no milestones, it says "The project has no milestones.".

The copied text includes the summary, the list of late critical tasks and the milestones with their date and variance, ready to paste into an email.

If the report can't be calculated

If the plan has a problem that prevents calculating the dates, the summary says "The project schedule could not be calculated (check the dependencies and dates).". Review the latest dependencies and dates you changed in the Gantt or the List.