Record progress

Report the progress percentage and the actual start and finish dates of each task so the plan reflects what's happening.

On this page

During the project, each assignee reports how far along their task is and when it actually started or finished. With that, Elion ITSM calculates the progress of the phases and the project, detects late critical tasks and adjusts the dates of what's coming.

Before you start

  • You must be a Lead or Member of the desk.

  • Progress is recorded on tasks and milestones. Phases and tasks with subtasks calculate their progress from their rows.

  • If the task has a linked epic, its progress comes from the epic and isn't entered by hand. See Link an epic from an agile board.

Record progress quickly in the list

  1. Go to List.

  2. In the task's Progress column, enter the percentage (0 to 100) and press Enter or leave the cell.

  3. On a milestone, check the Met checkbox.

Record progress and actual dates

  1. In the List or the Gantt, press the task's Edit pencil.

  2. In the Plan section, adjust Progress (%).

  3. In the Actual section, fill in:

    • Actual start: the day the task actually started.

    • Actual finish: the day it finished.

  4. Press Save.

If you fill in Actual finish without touching the progress, the task goes to 100% automatically.

How actual dates change the plan

  • With an Actual start, the task has already started: its start is set to that day and its predecessors no longer move it.

  • With an Actual finish, its finish is set to that day and it's no longer on the Critical path.

  • Successors are recalculated from the actual dates. If a task finished early, the ones that depend on it can move earlier; if it finished late, they shift later.

  • The Actual finish can't be earlier than the Actual start.

The task status follows the progress

You don't have to change the status by hand: Elion ITSM adjusts it based on what you report.

You report

The task becomes

Progress greater than 0 or an Actual start

In progress

100% progress or an Actual finish

Completed

You lower the progress from 100%

Goes back to In progress (or to Planned if it ends at 0 with no actual start)

A task in Blocked keeps that status while you change its progress, until it reaches 100% or you set an Actual finish: then it moves to Completed.

How phase and project progress is calculated

  • A phase's progress is the average of its rows, weighted by each one's Effort (hours). Rows with no effort weigh according to their duration.

  • The Gantt's Progress indicator applies the same rule to the whole project.

  • The progress expected by today depends on how much of each task's working time has already passed. If a critical task is more than 15 points below what's expected, it's considered late.

If your plan includes the Elion assistant, you can also ask it to update a task's progress, for example "set OBRA-7 to 60%". You still need to be a Lead or Member of the desk. See Elion assistant.