Critical path

Identify the tasks that have no slack, where any delay pushes back the project finish.

On this page

The critical path is the chain of tasks and milestones that has no slack: if one of them is delayed by a day, the project finishes a day later. The other tasks have slack and can shift a little without moving the finish. Elion ITSM calculates it on its own every time the plan changes.

How Elion ITSM calculates it

  1. Using the durations, the Dependencies between tasks and the Date constraints, it calculates the earliest each task can start and finish, in working days.

  2. From the project finish, it calculates the latest each one can finish without delaying the finish.

  3. The difference between the two is the slack. Tasks with zero or negative slack are the critical path.

Some details:

  • A task with an Actual finish is already done and is never critical.

  • A Finish no later than or Fixed constraint reduces slack and can make a task critical even if it isn't at the end of the project.

  • A phase shows as critical if any of its rows is.

Where you see it

  • Gantt: the bars, diamonds and arrows on the critical path are painted red, and so is the row's WBS number. The legend shows it as Critical path.

  • On critical path indicator: above the Gantt, how many tasks and milestones are on the path.

  • List: the row has the critical tag in the Type column and a red border next to the name.

  • Milestones: a critical milestone has the critical tag.

Late critical tasks

A critical task is late when it has no actual finish and also:

  • its finish date has already passed, or

  • its progress is more than 15 points below what's expected for today (for example, it should be at 60% based on elapsed time and it's at 40%).

These tasks appear in the Late critical tasks section of the Status report. Since they have no slack, every day they stay late pushes back the project's Planned finish and increases the Variance against the baseline.

What to do with a late critical task

  • Update its progress to find out if it's really late (see Record progress).

  • Check if any of its successors can start earlier with a Start → start dependency or with a lead (negative lag).

  • Check the Workload per person: an overallocated person often explains the delay.

If your plan includes the Elion assistant, you can ask it what would happen to the project finish and the milestones if a task is delayed a few days, without changing the plan. See Elion assistant.