Team metrics
An agile board's velocity, lead time, cycle time, throughput and cumulative flow, over the date range you choose.
Metrics show how the team works over time: how much it delivers, how long it takes and where work piles up. They help you plan with data and find bottlenecks.
Before you start
Anyone who can see the desk can open its metrics.
Open the metrics
Go to Desks, choose the desk and press Metrics.
By default you see the last 90 days. To change the period, choose From and To and press View.
From must be before To. Otherwise, you see The "From" date must be before "To".
The indicators at the top
Indicator | What it measures |
|---|---|
Lead time · median | Days from when an item is created until it reaches Done. Half of the items take that long or less |
Lead time · p85 | 85 % of the items take that long or less. Useful for committing to dates with a margin |
Cycle time · median | Days from when an item first enters In progress until it reaches Done |
Cycle time · p85 | 85 % of the items take that long or less from when they are started |
Done per week | Average number of items finished per week in the period |
An item that never went through In progress counts for lead time, but not for cycle time.
If lead time is much higher than cycle time, items wait too long before starting: check the size of the backlog or of the To do column.
The charts
Velocity (Scrum only): for each closed sprint, a Committed bar and a Completed bar. It appears when the first sprint is closed. If Completed always stays below Committed, the team is over-planning.
Throughput: how many items were finished each week (Done).
Cumulative flow (CFD): one band per status, in the order of the board's columns, with how many items were in each status each day. If a band widens, work is piling up in that status.
Below each chart, Show data shows the same values in a table.