Projects
Waterfall project desks with phases, tasks, milestones, dependencies, critical path, baseline and workload per person.
On this page
A waterfall project desk is a complete project: you split it into phases, tasks and milestones, you link the tasks that depend on each other, and Elion ITSM calculates the dates, the critical path and the planned finish using the working days of the project calendar. When the plan is ready, you snapshot it as a baseline so you can later measure how much it slipped.
Each project desk is one project. You find it in the side menu, under Desks, with the project name. When you open it, it goes straight to the Gantt, and its four views appear below its name.
View | What it's for |
|---|---|
Gantt | See and adjust the plan over time: bars, dependencies, critical path, baseline and project indicators |
List | Build and edit the plan as a table (the WBS, or work breakdown structure), row by row, also with the keyboard |
Milestones | See the milestones on a monthly calendar and check which are on track, slipped, overdue or met |
Workload | See how many hours each person has assigned against their capacity, in this and other projects and agile boards |
If you are the Lead of the desk, you also see Settings.
What you can do depending on your role
View the project: your role needs access to Project desks and you must be able to see the desk.
Change the plan (create rows, move dates, dependencies, progress, link epics): you must be a Lead or Member of the desk. With the Viewer desk role you can only look.
Snapshot and choose the baseline: only the desk Lead.
Anyone with Administer on Desks, groups, rules, categories, services and organization acts as Lead on the project desks they can see.
Status report: you only need to be able to see the project, but your company's plan must include the Elion assistant.
If the desk is archived, the project is read-only for everyone.
In New desk, the Waterfall project template still shows as Coming soon. This guide covers the project desks that already exist in your company.
How the plan is calculated
Everything is counted in working days according to the project calendar: weekdays with no schedule and holidays don't count. Calendars and their holidays are defined in Settings → Calendars.
The server calculates the dates. When you change a duration, a date or a dependency, Elion ITSM recalculates the tasks that come after and the critical path, and tells you how many successors moved.
Phases have no dates of their own: their start, finish, effort and progress come from the rows they contain.
If someone else changes the project while you are looking at it, the view updates on its own.
Suggested order to build a project
Build the plan in the list: create the phases and, inside each one, their tasks with duration, assignee and effort. Add the milestones.
Dependencies between tasks so one starts when another finishes.
If a task has a date that can't move, give it a Date constraints.
Check in the Use the Gantt how it turned out and which tasks are on the Critical path.
When the plan is approved, Baseline.
During the project, Record progress and review the Milestones and the Workload per person.
Each week, prepare the Status report and share it.