Close a sprint and hold the retrospective
Close the active sprint, decide where unfinished work goes and record the team's review and retrospective.
On this page
When you close a sprint, the platform records the completed points, moves what was left pending and saves what the team discussed in the review and the retrospective. Improvement actions can become items for the next sprint.
Before you start
You must be the desk's Lead.
Only the active sprint can be closed.
If you want to move pending work to another sprint instead of the backlog, create it first. See Create and plan a sprint.
Steps
Go to Sprints and press Close sprint on the active sprint's card, or open it and press Close sprint at the top.
In the Close window, at the top you see how many points were done out of the total.
In Unfinished work moves to, choose The backlog or one of the planned sprints.
In Review: what was demonstrated, note what the team showed in the sprint review.
In the Retrospective part, write one idea per line in:
What went well (one idea per line).
What to improve (one per line).
Actions (one per line; they can become items).
Press Close sprint.
You don't need bullets: each line is saved as a separate point. Empty lines are ignored.
What happens next
You see the notice that the sprint was closed and how many items moved to the backlog or the next sprint.
Unfinished items, with their subtasks, go to the destination you chose. They keep their status.
Those that go back to the backlog stay at risk until you plan them again in a sprint.
The sprint moves to Closed, with its completed points against those committed. Its velocity goes into the team's average and into the Team metrics.
You can now Start a sprint.
See the retrospective and create items from the actions
Open the closed sprint from Sprints → Closed.
Scroll down to Retrospective. You see three columns: What went well, What to improve and Actions.
Next to each action, press Create item.
New item opens with the action as the title and the Task type. Adjust what you need and press Create.
The new item stays in the backlog, ready to be planned in the next sprint. To create items from the actions you must be a Lead, Member or QA.