Baseline
Snapshot the approved plan to later compare the actual dates and measure how many working days the project slipped.
On this page
The baseline is a snapshot of the plan at a given moment: it stores the start and finish dates and the effort of every row. It doesn't change when you move tasks, so you can use it to compare the current plan with what was committed and measure the variance.
Before you start
Only the desk Lead takes baseline snapshots and chooses which one is current.
The project must have at least one row.
It's best to take the snapshot when the plan has been reviewed and approved: phases, tasks, durations, dependencies and milestones.
Snapshot the baseline
Go to the project's Gantt.
Press Snapshot baseline.
In New baseline, check the Name. It's suggested as "Plan as of" plus today's date; change it if you want (for example, "Plan approved by the committee"). It allows up to 80 characters.
Press Snapshot the plan.
You'll see the message "Baseline “name” created".
The project's first baseline becomes current right away. Later ones are saved, but the current one stays the previous one until you mark another.
How it looks in the Gantt
Under each bar a gray ghost bar appears with the baseline dates. If the actual bar ends further right than the gray one, the task is behind the plan.
The Baseline checkbox in the toolbar shows or hides the gray bars.
The Variance indicator compares the project's Planned finish with the baseline finish.
Set another baseline as current
The current baseline is the one used by default for the variance, the milestones and the status report.
In the Gantt, open the Compare against selector (it appears when there is more than one baseline). The first option is Current with its name.
Choose another baseline. The Gantt is compared against it.
If you want it to be the reference for everyone, press Set as current.
You'll see the message "“name” is now the current baseline".
The selector shows the current baseline and the ones you snapshotted while you had the project open. If you close the page, it goes back to showing only the current one.
The Variance column
In List and Milestones, the Variance column shows the working days of difference between each row's current finish and its finish in the baseline:
Value | Meaning |
|---|---|
+3 d (in red) | Finishes 3 working days later than planned |
−2 d | Finishes 2 working days earlier |
0 d | Finishes on the planned day |
– | There's no baseline, or the row didn't exist when the snapshot was taken |
What happens next
Rows you add after the snapshot have no baseline until you take a new one.
If the project changes scope, take a new baseline snapshot and set it as current. The previous ones are kept.