Date constraints

Set whether a task or milestone should start as soon as possible, not before a date, finish on time or stay fixed on its date.

On this page

The constraint on a task or milestone tells Elion ITSM how to treat its dates when it recalculates the plan. Use it to reflect real commitments: an installation that can't start before the equipment arrives, a delivery with a contract date or a meeting that doesn't move.

Before you start

  • You must be a Lead or Member of the desk.

  • Phases have no constraint: their dates come from their rows.

The four constraints

Constraint

How it behaves

As soon as possible

Starts as soon as its predecessors and the project start allow. It's the constraint of every new row with no start date

Start no earlier than

Doesn't start before the constraint date, even if its predecessors allow it. If a predecessor is delayed, it still shifts forward

Finish no later than

Doesn't move the task, but marks the latest date it can finish. If the calculation leaves it finishing later, the task is in conflict and the Status report reports it

Fixed

The task starts exactly on the constraint date and doesn't move on its own. If a predecessor would push it further, it goes into conflict instead of moving

If the constraint date falls on a non-working day, the task starts on the next working day.

Set a constraint

  1. In the Gantt or the List, press the Edit pencil on the task or milestone.

  2. In the Constraint section, choose the constraint in Constraint.

  3. If it isn't As soon as possible, fill in Constraint date. The form won't save without it and warns: "That constraint needs a date.".

  4. Press Save.

Constraints that are set automatically

You don't always have to open the form:

  • Moving a bar in the Gantt or entering a Start in the list sets the task to Start no earlier than with that date.

  • If the task was Fixed, moving it changes the fixed date.

  • Clearing the Start of a task that was Start no earlier than or Fixed returns it to As soon as possible.

If you moved a task and now want it to follow only its predecessors again, edit it and choose As soon as possible.

How they affect the calculation

  • Start no earlier than and Fixed can leave gaps between a task and its predecessor: the task waits for its date.

  • Finish no later than and Fixed reduce the task's slack, so they can put it on the Critical path even if it isn't at the end of the project.

  • A task with an Actual start has already started: its start is that day and the constraint no longer moves it. See Record progress.