Build the plan in the list

Create phases, tasks and milestones in the List view, arrange them in the WBS and edit dates, duration and progress right in the table.

On this page

The List view shows the project as a hierarchical table, the WBS (work breakdown structure): phases that group tasks, and tasks that can have subtasks and milestones. It is the fastest way to build the plan and the best one to use with the keyboard or on narrow screens.

Before you start

  • You must be a Lead or Member of the project desk. With the Viewer role you see the table but can't change it.

  • It helps if the people who will be assignees are already desk members: the Assignee field only offers members.

The three row types

Type

What it is

Dates

Phase

Groups tasks (for example: Survey, Design, Build)

Calculated from its child rows; not editable

Task

Work with a duration, assignee and effort

Start, finish and duration in working days

Milestone

Zero-duration checkpoint (for example: "Design delivery")

A single date

Structure rules:

  • A phase goes at the top level or inside another phase.

  • A task can go inside a phase or inside another task (it becomes a subtask). A task that has subtasks is then calculated from them, just like a phase.

  • A milestone can't have rows inside it.

  • The WBS allows up to 10 levels and up to 2,000 rows per project.

Create the first phase

  1. Go to Desks, open the project and choose List.

  2. If the project is empty, you'll see "This project has no phases, tasks or milestones yet.". Press New row.

  3. Type already has Phase selected. Enter the Title (at least 3 characters).

  4. Press Create.

In the Gantt, an empty project shows the Create the first phase button, which opens the same form.

Add tasks and milestones

  1. On the phase row, press the + button (New row inside the phase). You can also press New row at the top and choose the phase in Inside.

  2. Fill in the New project row form:

    • Type: Phase, Task or Milestone.

    • Title: the name of the row.

    • Inside: the phase or task that contains it, or Top level of the project.

    • Start: leave it empty so the task starts as soon as possible given its predecessors. If you enter a date, the task won't start before that day.

    • Duration (working days): tasks only. Half days are allowed (for example, 2.5); the Gantt rounds up. If you leave it empty, the task lasts 1 day.

    • Effort (hours): tasks only. These are the work hours spread across the Workload per person, and they weigh in the phase progress.

    • Assignee: on tasks and milestones, a desk member or Unassigned.

  3. Press Create.

Elion ITSM numbers the WBS (1, 1.1, 1.2, 2…), and each row also gets an item number (for example, OBRA-12) that opens its record.

You choose the assignee when you create the row. The list and the Gantt show it, but don't change it.

Edit right in the table

Each editable cell saves when you leave it (or when you press Enter in text and number fields):

Column

What you change

Name

The row title (at least 3 characters)

Start

The date the task starts. It's the same as moving the task: it won't start before that day

Finish

The end date; Elion ITSM recalculates the duration in working days

Days

The duration in working days; Elion ITSM recalculates the finish

Progress

The progress percentage (0 to 100)

On a milestone, the Finish column is its date and Progress is replaced by the Met checkbox. On a phase, the dates, days and progress are display-only: they come from its children.

If the server rejects a change, the cell goes back to its previous value and a message explains why, for example "The finish cannot be before the start." or "There are no working days between the start and the finish".

To change several things at once (effort, actual dates or the Date constraints), press the Edit pencil on the row. On a phase, that form only changes the Title.

In the Edit form, change the Finish or the Duration (working days), not both at once: one is calculated from the other. If you change both, the server rejects the change with the message "Send the finish date or the duration, not both.".

Arrange the WBS

To the left of each row there are four buttons:

  • ↑ Move up and ↓ Move down: move the row among its siblings (those on the same level).

  • → Indent: the row becomes the last child of the row above.

  • ← Outdent: the row moves out one level and lands right after the row that contained it.

The buttons are disabled when the move doesn't apply, for example, to put a phase inside a task or a row inside a milestone. After the move, the focus stays on the same button, so you can repeat the move with the keyboard.

A task that already has dependencies can't be split into subtasks. First remove its dependencies, then indent rows inside it.

Collapse and expand

Rows that have children show an arrow next to the name. Press it to Collapse the row (hide its children) or Expand to see them again.

Other columns

  • Type: Phase, Task or Milestone. If the row is on the critical path, the critical tag is added and the row gets a red border.

  • Assignee: the assigned person.

  • Predecessors: the rows it depends on, with the dependency type and the lag (for example, OBRA-3 FS+2). See Dependencies between tasks.

  • Variance: the difference in working days against the Baseline.

  • The Epic button, on tasks, lets you Link an epic from an agile board.

What happens next

  • Phases are recalculated with the dates, effort and progress of their children.

  • If you changed dates or duration, Elion ITSM moves the tasks that depend on the row and tells you, for example, "OBRA-7 saved; 2 successors moved".

  • If someone else changed the same row a moment earlier, you'll see that the project reloaded; make the change again.

  • Press Gantt to see the result over time.