CAB approval

Request CAB approval for a normal or emergency change, track who approved and who's missing, and understand why standard changes don't go through the CAB.

On this page

The CAB (change advisory board) is the group of people who review a change before it's carried out: whether the plans are clear, whether the risk is acceptable and whether the window clashes with something else. In Elion ITSM, CAB approval is a workflow: the workflow creates the approval tasks, each member decides from My tasks and, with the decision, the change moves forward or is rejected.

Before you start

  • You need Operate in Changes and a desk role other than Viewer.

  • The change must be In assessment, that is, with its plans and window ready (see Change plans).

  • For Normal and Emergency changes, your company must have a published workflow that starts with that change type. An administrator builds it in Workflows (see Create a workflow).

How it works by type

Type

What happens

Standard

It's pre-approved. When you request approval, it goes straight to Scheduled, with no tasks for the CAB.

Normal

When it moves to In assessment, the approval workflow for normal changes starts. When you request approval, it becomes Awaiting CAB.

Emergency

Like normal, but with the workflow for emergency changes, which usually has fewer approvers and shorter deadlines. The CAB section shows Awaiting emergency CAB.

Request CAB approval

  1. Open the change record. It must be In assessment.

  2. Press Request CAB approval at the top.

  3. Depending on the type:

    • a Normal or Emergency change moves to Awaiting CAB and appears in the list's Awaiting CAB tab;

    • a Standard change goes straight to Scheduled.

The button says Request CAB approval on standard changes too, even though they don't go through the CAB. It's how you mark the assessment as finished.

From Awaiting CAB, the plan, the window and the rest of the classification can no longer be modified. The only status button left is Cancel change: the CAB makes the decision, not the record.

Track the approval in the CAB section

In the record's side panel, the CAB section shows how the approval is going:

What you see

What it means

Pre-approved · Standard changes don't go through the CAB.

It's a standard change.

Not requested yet · It's requested when moving from assessment to approval.

The change is in Draft or In assessment.

Awaiting CAB or Awaiting emergency CAB

The approval is in progress. Below it, the task name and how many have decided, for example "2 of 3 decided".

Awaiting CAB · Workflow "…" in progress.

The workflow is running, but hasn't opened the approval task yet (for example, it's on an earlier step).

Approved · The CAB approved the change.

The change is already Scheduled or further along.

Rejected by the CAB · The change won't be implemented.

The CAB rejected it.

While waiting for the CAB you also see:

  • Rule: how it's decided. one approval is enough, everyone must approve or majority decides, depending on how the workflow is built.

  • The list of approvers, each with Approved, Rejected or Pending.

  • The Go to My tasks button, for whoever has to decide.

The section updates on its own every time someone votes.

Approve or reject as a CAB member

  1. Go to My tasks in the side menu, or press Go to My tasks on the change record.

  2. Find the change's approval task. It shows the change number and title; click the number to review it before deciding.

  3. Press Approve or Reject.

  4. In the window, write a Comment (optional) if you approve, or the Reason (required) if you reject. The person who requested the change will see it.

  5. Confirm with Approve or Reject.

More details in Workflows and tasks.

What happens with the decision

  • If the CAB approves, the change moves to Scheduled and can be implemented in its window (see Implement and review a change).

  • If the CAB rejects, the change moves to Rejected. It's a final state: it isn't edited or reopened. If it's worth trying again, record a new change with the adjustments the CAB asked for.

  • If the change came from an agile board release, the release goes out when the change is approved, or goes back to In progress if it's rejected (see Release a version).

No approval workflow attached

If in the CAB section you see No approval workflow attached: check the change workflows., the change is awaiting the CAB but there's no published workflow for its type, so no one got the task to approve it.

A change in that situation doesn't move forward on its own. Ask an administrator to publish in Workflows a workflow that starts with changes of that type. Since the workflow starts when moving to In assessment, for a change that's already waiting the simplest thing is to cancel it and record it again once the workflow is published.