DocumentaciónHelp

Milestones

Create milestones, review them on the monthly calendar and track which are on track, slipped, overdue or met.

On this page

A milestone is a zero-duration project checkpoint: a delivery, an approval or a go-live. The Milestones view shows them on a monthly calendar and in a list with their status and their variance against the baseline.

Before you start

  • To create or change milestones, you must be a Lead or Member of the desk.

  • For a milestone to show as Slipped, the project needs a Baseline.

Create a milestone

  1. Go to the project and choose Milestones.

  2. Press New milestone. The New project row form opens with Type set to Milestone.

  3. Enter the Title and choose Inside (the phase it belongs to).

  4. In Start, enter the milestone date. If you leave it empty, the milestone lands on the date its predecessors allow.

  5. If needed, choose the Assignee.

  6. Press Create.

Usually a milestone depends on the last task of a phase: create a Finish → start dependency from that task to the milestone, and the milestone will move on its own if the phase is delayed. See Dependencies between tasks.

Change a milestone's date

  • In the List, change the date in the milestone's Finish column.

  • In the Gantt, drag the diamond or move it with the keyboard arrows.

  • With the Edit pencil, change Milestone date. The same form has Met, Actual date and the Date constraints.

Mark a milestone as met

  • In the List, check the milestone's Met checkbox.

  • Or press Edit, check Met and, if you want to record the day it was met, fill in Actual date. Press Save.

The Milestones view

The totals are at the top: Milestones, Met, Overdue and Slipped.

Monthly calendar

  • Each milestone appears as a label on its day, colored by its status. Click the label to open the milestone record.

  • Non-working days are shaded and today is highlighted.

  • Use Previous month, Today and Next month to move around. When you open it, the calendar shows the month of the next pending milestone.

Milestone list

Below the calendar, the table has the columns Date, Milestone, Phase, Status, Baseline and Variance. Click a date to see that month in the calendar. A milestone on the critical path has the critical tag.

Filter the table with:

  • All: all milestones.

  • Pending: those not met.

  • Overdue and slipped: those that need attention.

Milestone statuses

Status

When

Met

It was marked as met (100% progress)

Overdue

Its date has passed and it isn't met

Slipped

Its date hasn't arrived yet, but it's after the baseline date

On track

Its date hasn't passed and it isn't after the baseline

No date

It doesn't have a date yet

The Variance is the working days between the milestone's current date and the baseline date: +2 d in red means it slipped two working days.

"Today" is measured in the time zone of the project calendar, not your computer's.

Related

Search Elion ITSM

Type at least 2 characters to search Elion ITSM.

↑↓ to navigate · Enter to open · Esc to close