Schedule the management review
Schedule the management review; SofIA Governance automatically assembles its inputs from the current state of the ISMS.
When you schedule a meeting, SofIA Governance gathers what management must review according to ISO 27001 9.3, with the ISMS data at that moment. You don't have to prepare the presentation by hand.
Before you start
You need the Editor or Administrator role.
It's best to have the committee set up. See Set up the committee. You can also schedule without a committee.
Steps
Go to Governance → Meetings and management review.
Press Schedule meeting (or Schedule the first one, if there are no meetings yet).
Leave the Type as Management review.
Choose the Committee. The first active committee is preselected; with — No committee — the meeting has no members.
Type a Title if you like (for example, “Management review 2026”).
Enter the Date and time (required) and, if you like, Notes for the notice.
Press Schedule.
What happens next
You'll see Meeting SES-0001 scheduled. Its inputs are ready. (with the code it was assigned) and the meeting's record opens. The record has four tabs: Review inputs, Decisions, Minutes and evidence and ISMS version.
Committee members see the meeting in My work and, depending on their notification preferences, receive an alert a few days before.
What the inputs contain
In Review inputs you'll find:
Input | What it shows |
|---|---|
a) Status of actions from previous reviews | The decisions from previous meetings, whether they're done, open or overdue, and the progress of the plans they led to. |
b) Changes in context | Whether the ISMS scope changed, the standards adopted during the period and how many assets, processes, services, suppliers, data processing activities and people were added or modified. |
c) ISMS performance | Indicators, nonconformities, corrective actions and their effectiveness, audit results, achievement of objectives (progress of each standard and indicators on target) and incidents, with personal data breaches. |
d) Risks and their treatment | Current risks, those above the acceptable level, without treatment or accepted, new ones and the highest ones. |
e) Improvement opportunities | Open improvement findings and improvement plans in progress. |
Above the inputs you see the Period they cover and when they were assembled. The period runs from the last management review held (or from the start, if it's the first one).
If you scheduled well in advance, press Rebuild before the meeting to take that day's data. You'll see Inputs updated. Once the meeting is closed, the inputs are Frozen in the minutes and no longer change.